| Name
of Plant : |
640 MW
Leyte-Cebu (200 MW) & Leyte-Luzon (440 MW) Geothermal Power Plant (A19
& A21) |
|
| Name of IPP : |
PNOC-Energy Development Corporation |
|
| Contract Type : |
Build-Operate-Transfer/Power
Purchase Agreement/Solicited |
|
| Status of Plant : |
Operational |
|
| Cooperation Period : |
25 years - Leyte-Cebu (July
1996 - July 2021)
Leyte-Luzon (August 01, 1997 - August 01, 2022) |
|
| |
|
|
| Nature of Issue |
Issue |
Recommendation |
| Fee Structure |
Components
of the escalation factor may have contributed to higher IPP rates.
|
Validate
the components of the escalation adjustment for possible modification of
inflation factor.
|
| |
Mismatch
of PPA's 25 years cooperation period over ECA's 10 years cooperation period
may have brought about higher IPP rates over NPC's production costs. |
Energy
Regulatory Commission (ERC) to unbundle energy fees in order to determine
possible price component modification. |
|
|
|