5-8 AUGUST 2002
Trail of Power Mess Leads to Ramos

[SOURCE: IPP REVIEW COMMITTEE REPORT]

Name of Plant : 50 MW General Santos Bunker Coal-Fired DieseI Power Plant Project (A27)  
Name of IPP : Alsons Power Holdings Corporation & Tomen Corporation  
Contract Type : Build-Operate-Own/Energy Conversion Agreement/Solicited  
Status of Plant : Operational  
Cooperation Period : 18 years (December 1997 - December 2015)  
     
Nature of Issue Issue Recommendation
Fee Structure With a low dispatch level, the power plant is not utilized to its full potential and its "wear and tear" is considerably slower. This means that the replacement cost of the plant parts embedded in the tariff structure may have been lowered. The Fixed O & M portion of tariff is pegged at the maximum capacity regardless of dispatch level. Therefore, whether or not the power plant is operating to its full potential, the full fixed O & M fees are paid by NPC. NPC to negotiate restructure of O & M fees from fixed cost to variable cost