| Name
of Plant : |
304 MW San
Pascual Cogeneration Production Facility (A29) |
|
| Name of IPP : |
San Pascual Cogeneration Co. (Texaco, Inc., Edison Mission
Energy, SPCC International B. V. Netherlands and SPCC Philippines) |
|
| Contract Type : |
Build-Operate-Own/Power Purchase Agreement/Unsolicited |
|
| Status of Plant : |
Pre-Construction
Stage |
|
| Cooperation Period : |
25 years (January 2001 - January 20216) |
|
| |
|
|
| Nature of Issue |
Issue |
Recommendation |
| Termination of the PPA |
PSALM and SPCC have agreed to pre-terminate the Power Purchase
Agreement. Both parties are negotiating for the Termination Agreement. |
We concur with PSALM regarding its decision to terminate the
PPA. In the long-term, it would be more advantageous to NPC to reimburse the
development costs of SPCC rather than pay for capital recovery fees, fixed
operating and maintenance fees, energy fees and fuel costs during the 25-year
cooperation period. |
| Termination (Settlement) Agreement |
The
final Termination Agreement between PSALM and SPCC is yet to be concluded
including the return all the Development Bond and development costs incurred
by SPCC with regard to the project. |
PSALM should review closely the Termination Agreement. |
| |
|
|
| |
Other significant and
material items are yet to be agreed upon before the PPA will be officially
terminated. |
|
|
|
|